Sheathing Inspection

<<< On Site Checklists

  

Nail gun or screw guns ready
  • Be prepared to shoot off any locations your inspector calls out

Ladder access set up to second story
  • Some inspectors check visually from the outside, others hit on the walls from the inside
All sheathing installed
  • Corners tying walls together
  • Scabs in the rimboard between 1st and 2nd story
  • Gables and trusses covered
All necessary nailing complete
  • Into sill plates
  • Into rimboard
  • Into truss heels or frieze block
  • Structural straps